LIFETAN 24 month progress meeting
INESCOP premises, Elda, Alicante (Spain), 18th October 2017
INESCOP and ENEA welcomed all present beneficiaries (CNR-ICCOM, NEWPORT and TRADELDA) and started the meeting introducing the status of works for each participant for each ongoing action. The intervention was focused on the completion of activities, according to the new scheduled timing and preparing the 3rd monitoring visit (November the 22nd, at Newport premises).
Each participant presented the technical work carried out in the last 6 months of the project (from April 2017 to September 2017) and the actions of communication and dissemination of results. A visit of TRADELDA factory (leather finishing) has been carried out in the afternoon.